First pour in the Boric Acid circuit of the plant

11/03/2022

Containment wall forms ready to be stripped, now that PLS area pads are complete

11/03/2022

Rebar cages ready for installation once support piers are drilled out

11/03/2022

Continued Construction Work on Foundations, Piers, and Steel Erection

10/03/2022

5E is Continuing to Receive Process Equipment for Installation Once Foundations are Complete

10/03/2022

Continued Construction Work on Foundations, Piers, and Steel Erection

10/03/2022

Receiving FRP Tanks for Installation on Existing Platforms

09/12/2022

Installation of Steel Pipe Racks

08/29/2022

Construction of Tank Foundation Forms

08/29/2022

Level Surveying and Installation of Foundation

08/04/2022